Which of the following is NOT one of the five process groups?

Prepare for the SSGI Project Management Professional Certification Exam. Study with flashcards and multiple-choice questions, each with hints and explanations. Get ready for your certification journey!

The correct answer is "Evaluating" because the five process groups, as defined by the Project Management Institute (PMI), are Initiating, Planning, Executing, Monitoring and Controlling, and Closing. These groups outline the structured approach to project management.

Initiating involves defining and authorizing the project, while Planning focuses on outlining how the objectives of the project will be achieved. Executing is the phase where the project work is performed according to the project management plan. Monitoring and Controlling ensures that the project remains on track and makes necessary adjustments as required, and Closing formally completes the project, ensuring all aspects are finalized and the project is closed out properly.

"Evaluating," however, is not one of these recognized process groups. Although evaluation might occur within the Monitoring and Controlling phase as part of ensuring project performance and effectiveness, it is not independently listed as a separate process group. This distinction clarifies why "Evaluating" is not considered one of the five process groups in project management methodology.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy