Which project management approach is associated with a linear sequence of project phases?

  1. Agile

  2. Extreme

  3. Predictive

  4. Adaptive

The correct answer is: Predictive

The project management approach associated with a linear sequence of project phases is predictive. This methodology is characterized by a structured and sequential process where each phase must be completed before moving on to the next. This linear progression allows for careful planning, clear definition of requirements, and thorough documentation. In predictive project management, the project's scope, schedule, and resources are defined at the beginning, and changes are managed through formal change control processes. This approach is often contrasted with more iterative and flexible methodologies like Agile or Extreme, which allow for ongoing adjustments and refinements based on continuous feedback and evolving project needs. Predictive models are particularly effective in projects with well-understood requirements and low levels of uncertainty. As a result, they are commonly employed in industries such as construction and manufacturing, where predictable outcomes are paramount.